- 01The price of a job is made of materials, hardware and services, labour, overheads and margin. Tax is added at the end, if you charge it.
- 02Boards are costed per m² with a waste allowance, or as whole boards from the nesting. Edge tape is costed per metre, and a worktop per running metre.
- 03Hardware is copied from the hardware list, with screws and small fittings. Every item you forget comes out of your earnings.
- 04Labour is the hours for measuring, design, making, transport and fitting, times your hourly rate. Your past jobs are the best estimate of the hours.
- 05Overheads are workshop costs that do not belong to one job, such as premises, machines, a van and bookkeeping. They go into the hourly rate or into a surcharge on the job.
- 06The margin is your profit and a reserve for risk, and you decide how high it is. Tax depends on the rules in your country, so check how it is charged with your accountant.
Video transcriptthe narration as text
The same kitchen can be sold at a profit or at a loss. The difference is in the costing. In this lesson you'll see what the price of a job is made of, how each part is worked out, and how not to forget anything you'll later pay for out of your own pocket.
What a price is made of
You build a price from the bottom up. First the materials, then the hardware and the services you pay others for. On top of that comes your labour, then the overheads, the workshop costs that don't belong to any one job. Last comes the margin, and tax is added if you charge it.
The costing is for you, and the quote is for the customer. In the costing you see every item and what it costs. The customer sees the price, but not your purchase prices or your margin.
Materials
The biggest item is usually the board itself. It can be costed per square metre with a waste allowance, or by the whole boards you actually need. You buy whole boards, and what's left isn't always usable, so costing by whole boards comes closer to the real cost.
Along with the boards for the carcasses and fronts come the backs and the drawer bottoms. Edge tape is costed per metre, along the full length of each edge. A worktop is costed per running metre, and in a corner both worktops are counted at full length, because that's how they're bought.
Hardware and services
Copy the hardware from the hardware list, including all the screws and small fittings: the hinges, runners, legs, kickboard clips, handles, hangers and worktop connectors. Then also add the services you pay other people for, for example cutting and edge banding at the board supplier, or transport and delivery.
Every item you forget comes out of your earnings, because the customer won't pay for it. What gets forgotten most often are the small things, such as the screws, the silicone, the hanging rail or the delivery.
Labour
Labour is the number of hours times your hourly rate. The hours aren't only the making in the workshop. They also include the measuring and the design, then cutting, edge banding and drilling, assembly, transport and fitting. You set your hourly rate yourself, based on your costs and your market.
Your past jobs are the best estimate of the hours. Write down how long each kitchen really took, and compare it with the costing. After a few jobs you know how long a cabinet takes, and how long the fitting takes.
Overheads
Overheads are the workshop costs that don't belong to any one job: the premises, power, machines and tools, a van, insurance, bookkeeping and software. The time spent on quotes the customer doesn't accept is an overhead too. If you don't spread the overheads over your jobs, you end up paying them out of your own earnings.
You can build the overheads into your hourly rate, so every hour of work carries part of the workshop costs. Or you add them as a separate surcharge on the job. What matters is that they're included.
Margin and tax
The margin is your profit and a reserve for risk: a mistake, a complaint or a delay. How high a margin you set depends on the job, the market and the risk. That's your decision, not a fixed rule.
An example, with made-up round numbers, just to show the order of the calculation. Materials and hardware come to one thousand, and labour with overheads to five hundred. That's fifteen hundred. With a margin of ten percent, another hundred and fifty is added, so the net is sixteen hundred and fifty. Tax is added on top of the net.
Tax depends on whether you're registered for value added tax or a similar tax, and on the rate in your country. Check how it's charged, and what has to appear on the quote, with your accountant.
In short
In short. The price of a job is made of materials, hardware and services, labour, overheads and margin, and tax is added at the end. Cost the boards per square metre with waste, or as whole boards, the edge tape per metre, and the worktop per running metre. Copy the hardware from the hardware list, because every item you forget comes out of your earnings. Labour is the hours times your hourly rate, and your past jobs are the best estimate of the hours. Spread the overheads over your jobs. And you decide how high the margin is, while the tax is something to check with your accountant.
In Easy Form Studio, the Cost estimate panel adds up the boards, edge tape, hardware and machining at the prices in your price list. That's the purchase cost, without labour or margin. A green dot means an item has a price, and a red dot means it doesn't.
Labour is entered as one amount for the whole project, so work out the hourly rate yourself. The margin is calculated on the materials, edge tape, hardware and labour, and tax on the net. The internal calculation shows every item, and the customer quote only the price of each cabinet.
With nesting turned on, Easy Form Studio lays the parts out on the board sizes, and the quote counts whole boards instead of square metres. You enter the board prices and sizes in your price list.
The tutorials A quote for the customer, and Nesting and board prices, show all of this.
The three-question quiz and the summary are on the academy website; the link is below the video. In the next lesson: the quote and the agreement with the customer, the deposit, deadlines and changes.